You can add multiple demand charges to your tariff. Click on the Add Rate button on the left corner under the demand tab.

TB_Demand_add_Rate

 

 

This would open up a pop-up window that looks like below:

 

tb10

 

 

Follow the below steps to add a demand rate.

 

Step 1: Enter the name of the demand rate

tb11

Step 2: Choose the units of the demand rate.

The choices are: kW, kVA,and kVAR

 

tb12

Step 3: Specify the cost

 

1.Flat demand rate - If it is a constant energy rate ($/kW) then enter the price in box for cost

tb13

2.Tiered energy rate- If it is a tiered energy rate, then check the box that asks “Has Tiers”. This would display a table for you to enter the tiers and their costs. Enter the Limits for each Tier and the costs in $/kW. Make sure to enter a last tier with a really big number to indicate any demand above the last threshold.

dr-5

 

 

 

Step 4: Specify the Period

a.Select the interval over which the utility calculates the peak demand. The options are 15-, 30- or 60-minute peak demand intervals.

Note: If you are using a higher resolution load (for example, 15 minute interval data), but have kept the peak demand interval to 60 minutes, HOMER will average the load over 60 minutes to determine the peak. If you select a peak demand interval to be sub-hourly, use load data which has the same time-step length.

tb14

b: If this rate to only apply during the summer season, then change the FROM and TO dates accordingly.

dr-6

c: The default demand rate is a monthly demand rate. This means that a new peak demand is calculated every month, and that is the amount for which the customer gets charged. If this demand rate considers a ratchet peak, then select the box named "Has Ratchet?"

dr-7

i: If you chose “Has Ratchet”, then you need to specify the ratchet period over which the peak demand is calculated

dr-8

The example above shows a summer ratchet, where the peak is calculated from the months of May 1st - Aug 31st. This peak is applied for the whole year. So every month, irrespective of what the monthly peak demand is, the customer is charged based on the ratchet peak.

 

d: If this rate has a Time of Use, then you could check the box that says “Has Time of Use”, and this would allow you to add multiple times periods to this rate.

cr-8

 

 

Select a Range of TOU in Number of Days in a week, and the time during each of the selected days.

 

Step 5: Specify if this rate applies during Holidays

 

tb15

 

If this is checked, it would mean that this rate would be applied to any grid purchases during the holidays. To add all the public holidays in your region, go to the Add Holidays Section.